Pg 16 - Cutting & inserting the fiberglass
wall frp15/2/05-Here is a  shot of the other, smaller, panel frames awaiting their fiberglass and GOM. The adhesive and GOM are on the floor.
wall frp 25/2/05 - I’m starting with the largest panels and here is one of the 48" x 48" front sidewall units.
wall frp 35/2/05-Here is the 2" OC SelectSound Black cut to size and ready for adhesive.
wall frp 45/2/05-Applying the glue . . .
wall frp 55/2/05 . . . fiberglass glued in place.